JHS Project Update-2/6/24

Here is your weekly JHS Construction Update. 

New Build

Good day All!

 

Things are really starting to take shape. The crew has made great strides on our siding assemblies, and it is looking sharp.

On the interior the majority of the drywall on first floor has been hung and finishing continues. Drywall is being hung on second floor. Rough in continues on second floor.

By the end of next week we should have a majority of the first floor primed for paint. We have a ground heater thawing out the ground at the front entry in hopes we can begin prepping for the ADA ramp at the front entry while we have mild weather.

 

  • Last Week:

     

    • Interior soffit framing (Area G)
    • Hang & tape (Area G)
    • MEP rough in continues (Area G)
    • Fire suppression (Area G)
    • Siding assemblies (Area G)
    • Roof detailing (Area G)
    • Insulation (Area G)
    • Duct Insulation (Area G)
    • Pipe insulation (Area G)
    • Front entry ramp prep (Area G)
  • This Week:

    • Interior soffit framing (Area G)
    • Hang & tape (Area G)
    • 2nd Floor MEP rough in continues (Area G)
    • Fire suppression (Area G)
    • Siding (Area G)
    • Insulation (Area G)
    • Shingle patch back (existing roof)
    • Paint (Area G)
    • Front entry ramp excavation (Area G)
  • Next Week:

Posted Tuesday, May 16, 2023